The Navoi plant
The contract used a 100 MW benchmark. The completed plant had 132 MWdc of modules and 115 MWac of installed equipment. Construction took one year.
Completion report · World Bank, 2024 ↗We invite a priced proposal for engineering, procurement, construction and financing of a solar plant with 100 MWp of DC module capacity. Site selection and final terms follow the partner’s response.
The red scale maps modelled specific PV yield from the Global Solar Atlas. Compare regions at this stage. A parcel will be selected after the partner’s technical and financial response.
Enlarge mapValues correspond to sample cells near the reference cities. Final design requires land, grid, dust and water assessments.
Select a month to see mean hourly global horizontal irradiance in a typical meteorological year and how daylight varies through the day.

Navoi’s appraisal estimated 4,620 m³ of water per year for wet cleaning. Choose a cleaning schedule using measured losses, rainfall, available water and the value of recovered output. Maintenance helps preserve performance; output still varies.
Primary source ↗
SATBA reported a large-plant connection requirement of at least twenty per cent of capacity for two hours. On a 100 MW connection basis, the example gives 20 MW and 40 MWh. The connection approval determines the final basis.
Primary source ↗Choose a sales route to compare its pricing basis, contractual commitments and payment risk.
Uzbekistan’s Navoi plant provides a working comparison. Its completion report separates total project cost, EPC expenditure and delivered output.
The contract used a 100 MW benchmark. The completed plant had 132 MWdc of modules and 115 MWac of installed equipment. Construction took one year.
Completion report · World Bank, 2024 ↗Use these proposed terms to price the offer. Land rights, the cash contribution and bank acceptance each require supporting documentation.
Two examples for comparing datasheets. Check module power, string voltage compatibility and AC output at site temperature for the chosen design.
Seven technical and commercial chapters with original documents, reference data and limits of comparison.
The offer should let the buyer compare price, performance, delivery dates and the effective cost of finance on a consistent basis.
Open the downloaded form on your computer, add equipment lines and save the completed copy for return through your business correspondence.
Consult the original datasets, disclosures and contracts behind the figures and comparisons.